Torrevieja extends Don Sento towers environmental report for two years

The extension preserves a procedural step for four buildings near Palangre, but does not authorise construction or remove legal obstacles.

TD
Torrevieja Diario newsroomPublished on 11 November 2026

Share this article

WhatsAppFacebookTelegram

Land beside Palangre cove, with an old building and apartments in the background

Torrevieja Town Council has extended the validity of the environmental report for the four Don Sento towers planned at the Palangre bend, beside Los Locos beach, by two years.

The extension preserves one procedural step in the project, but does not authorise construction or remove the legal obstacles affecting high-rise developments beside the sea.

The local governing board approved the extension on 26 October and mayor Eduardo Dolón signed the notice the following day.

The strategic environmental and territorial report concerns the detailed plan for allocation area 78 and was approved in November 2022.

A project constrained by coastal law

The council maintains that the essential circumstances of that assessment have not changed.

The extension prevents this procedural step from expiring while the project’s future depends on the applicable legal framework.

Judgments by Spain’s Supreme Court and the High Court of Justice of the Valencian Community on seafront towers in Torrevieja upheld the opposition of the Ministry for Ecological Transition.

The rulings affected other developments and constrain projects planned under the same planning rules.

Four buildings beside Palangre

The project submitted by Urbablanca envisages two hotel towers and two residential towers on a plot of 14,735 square metres.

The layout provides for a ground floor and 28 storeys, as well as the transfer of 2,500 square metres around the protected Casa del Palangre and other public spaces.

The favourable assessment required additional documentation before final planning approval, including an analysis of shadows, integration into the surroundings and treatment of palm trees.

It also requested a geotechnical study because of the water table.

TORREVIEJA DIARIO · NEWSLETTER

Your city, in your inbox.

Useful news and plans for Torrevieja and the surrounding area. Mondays at 08:00 and Thursdays at 18:00 (Europe/Madrid): two emails a week. In English, free and without the noise.

Your choice. Confirm your email and unsubscribe at any time.

Know someone who would find this useful? Share it.

WhatsAppFacebookTelegram

Keep exploring

Back to home →